Background
This construction project is located on the Tibetan Plateau, where extreme environmental conditions and the absence of grid access make power supply particularly challenging. The site relies entirely on diesel generators to support operations. It involves large-scale construction equipment with high power demand and strong load fluctuations, placing significant pressure on power stability, fuel consumption, and overall system reliability.
Solution
3 × PowerCat-YD250M + Sync 3 ×generator 500kVA
This hybrid solution ensures stable and reliable power supply for complex construction operations, while reducing fuel consumption, emissions, and operational costs—supporting a more efficient and sustainable bridge construction process.